Project Background

Click to enlarge
(Click Map to Enlarge)

Over $24 million worth of pavement rehabilitation or reconstruction has been identified for local roads throughout the City.  At the City Council Meeting on June 2, 2016, the Council approved the use of bond funding for an extensive pavement rehabilitation program.  In total, $9 million was approved by the Council.  These bonds have been issued and are now available for the City to use.

The City split the program into eight phases of pavement rehabilitation or reconstruction of local neighborhood roadways.  Please see the above map for where these projects will be taking place for a visual illustration.  Each of the phases will target roughly $1 million in roadway work.  For more information about specific temporary closures and/or delays due to construction, drivers are encouraged to visit this page or go to www.jurupavalley.org/traffic.
 

PHASE 1

Contractor: Hardy & Harper, Inc.

Contract Amount: $1,292,000

Schedule: Construction began 11/7/2016 and will continue until 12/30/2016.

Click here to see project location map.

PHASE 2

Contractor: All American Asphalt, Inc.

Contract Amount: $618,500

Schedule: Construction January 3, 2017 through February 2017.

Click here to see project location map.

PHASE 3

Contractor: Hardy & Harper, Inc.

Contract Amount: $697,000

Schedule: Construction to start mid to late January 2017.

Click here to see project location map.

PHASE 4

Contractor: Hardy & Harper, Inc.

Contract Amount: $1,395,000

Schedule: Scheduled to begin construction by beginning of April, 2017

Click here to view project map

PHASE 5

Contractor: RJ Noble Company

Contract Amount: $1,039,758.50

Schedule: Construction May 15, 2017 through July 2017.

Click here to view project location map

PHASE 6

Contractor: All American Asphalt, Inc.

Contract Amount: $920,000

Schedule: Constrction June 19, 2017 through August 2017.

Click here to see project location map

Project Updates

06/28/2017 - Pavement reconstruction for Phase 6 has begun.  Please observe all posted traffic control.

06/09/2017 - Paving operations for Phase 5 has begun.  Please observe all posted traffic control.

06/08/2017 - The City of Jurupa Valley conducted a pre-construction meeting for Phase 6 at City Hall.

06/02/2017 - Construction on Phase 4 has been completed

05/31/2017 - Grinding and pavement reconstruction for Phase 5 has begun.  Please observe all posted traffic control.

05/18/2017 - The City of Jurupa Valley awarded the contract for Phase 6 of the City-wide Pavement Rehabilitation Project to All American Asphalt, Inc.

04/27/2017 - The City of Jurupa Valley conduced a pre-construction meeting for Phase 5 at City Hall.

04/06/2017 - The City of Jurupa Valley awarded the contract for Phase 5 of the City-wide Pavement Rehabilitation Project to RJ Noble Company.

03/23/2017 – Due to the construction of Phase 4, 46th Street between Jensen Ranch Road and Fort Drive will be temporarily closed beginning Monday, March 27, 2017 through Saturday, April 1, 2017.  Please follow the posted detours.

03/13/2017 – Construction on Phase 4 began.  The contractor has notified impacted residents and businesses and preparing streets for their specified improvement.

03/09/2017 – The City of Jurupa Valley conducted a pre-construction meeting for Phase 4 at City hall.

02/22/2017 - Construction for Phase 1 on Pyrite St was completed between the nights of February 19th and 20th. Striping and utility adjustments will be following shortly.

Construction for Phase 2 on Jurupa Rd and adjacent streets has been substantially completed.  Striping will be following shortly.

Construction for Phase 3 in the Glen Avon community has been substantially completed.  The installation of new AC Dike and shoulder backing is taking place throughout this week.  Striping will be following shortly.

02/16/2017 – The City of Jurupa Valley awarded the contract for Phase 4 of the City-wide Pavement Rehabilitation Project to Hardy & Harper, Inc.

01/20/2017 - Construction for Phase 1 on Country Village Rd was completed between the nights of January 16th and 17th. Paving on Pyrite St from SR60 to Granite Hill is scheduled for the nights of January 17th and 18th, weather permitting.  Striping and utility adjustments will be following shortly thereafter.  Construction for Phase 2 on Jurupa Rd and adjacent streets continued with the grinding as well as removing and replacing failed asphalt in preparation of a new asphalt overlay.

01/03/2017 - Construction on Phases 2 and 3 began.  The contractor is notifying impacted residents and businesses, marking out areas of improvement, and sealing cracking in the existing pavement.

12/21/2016 - The City of Jurupa Valley conducted a pre-construction meeting for Phase 3 at City Hall.

12/19/2016 - Construction for Phase 1 on Country Village Rd and Pyrite St from SR60 to Granite Hill has been delayed until mid-January 2017 due to the night time temperatures being too low to pave.  Granite Hill, Hudson St, and Pyrite from Lone Trail to SR60 are substantially complete with striping and utility adjustments remaining.

12/15/2016 - The City of Jurupa Valley awarded the contract for Phase 3 of the City-wide Pavement Rehabilitation Project to Hardy & Harper, Inc.

12/13/2016 - The City of Jurupa Valley conducted a pre-construction meeting for Phase 2 at City Hall.

12/12/2016 - The Hudson Street closure has been extended through Tuesday, December 13, 2016

11/28/2016 - Hudson Street between Limonite Avenue and 59th Street will be temporarily closed from Monday, December 5, 2016 through Friday, December 9, 2016, due to the Citywide Pavement Rehabilitation Project – Ph. 1. Please plan on using an alternate route or following the posted detours.

11/21/2016 - Granite Hill Drive between Camino Real & Valley Way will be temporarily closed from Monday, November 28, 2016 through Friday, December 2, 2016, due to the Citywide Pavement Rehabilitation Project – Ph. 1. Please plan on using an alternate route or following the posted detours.

11/17/2016 - The City of Jurupa Valley awarded the contract for Phase 2 of the City-wide Pavement Rehabilitation Project to All American Asphalt, Inc.

11/14/2016 - Pyrite Street between Mission Boulevard & the SR 60 Freeway will be temporarily closed from Monday, November 14, 2016 through Friday, November 18, 2016.  Visit the traffic management page at www.jurupavalley.org/traffic to see detour options.

11/7/2016 - Construction on Phase 1 began.  The contractor is notifying impacted residents and businesses, lowering utilities, and putting Storm Water Pollution Prevention Plan (SWPPP) devices in place.

10/13/2016 - The City of Jurupa Valley conducted a pre-construction meeting for Phase 1 at City Hall.  

9/1/2016 - The City of Jurupa Valley awarded the contract for the Phase 1 of the City-wide Pavement Rehabilitation Project to Hardy & Harper, Inc.


For any questions regarding the specific projects or the program as a whole, please contact Chase Keys with the City of Jurupa valley at (951) 332-6464 x235.