City-Wide Pavement Rehabilitation

Pavement Rehabilitation

Over $24 million worth of pavement rehabilitation or reconstruction has been identified for local roads throughout the City. At the City Council Meeting on June 2, 2016, the Council approved the use of bond funding for an extensive pavement rehabilitation program. In total, $9 million was approved by the Council. These bonds have been issued and are now available for the City to use.

Project Phases

Local Streets Rehabilitation Program Map (JPG)

The City split the program into eight phases of pavement rehabilitation or reconstruction of local neighborhood roadways. Please see the above map for where these projects will be taking place for a visual illustration. Each of the phases will target roughly $1 million in roadway work. For more information about specific temporary closures and/or delays due to construction, drivers are encouraged to visit the traffic page.

  1. Phase 1
  2. Phase 2
  3. Phase 3
  4. Phase 4
  5. Phase 5
  6. Phase 6
  7. Phase 7
  • Contract Amount: $1,292,000
  • Contractor: Hardy and Harper, Incorporated
  • Schedule: Construction began November 7, 2016 and will continue until December 30, 2016
  • View the project location map (PDF).